Installation of bypass valve should be performed in accordance with the installation instructions and taking into account the recommendations below.
A strainer filter is recommended to be installed before the bypass valve.
Pressure gauges should be installed before and after the valve to monitor the activation pressure.
The bypass valve body should not be subjected to tension, torsion, bending, or compression loads from connected pipelines.
Different manufacturers provide different data, but on average, it is recommended to maintain straight sections of 5DN before and 10DN after the valve.
The bypass valve can be installed on a horizontal, vertical, or inclined pipeline, unless otherwise specified in the installation instructions.